- 0.56q-02 · #01
Will SMA ship 3× STP 10.0 before 22 Sep?
Best guess · low · taken
No — SMA quoted 28 Sep, six days after the pull-in we need.
- Yes if we take 8.0s from stock and rewire the strings.
- Buy used 10.0s from Pier 2 this week.
- 0.57q-03 · #02
Does the co-op still own the north-shed meter?
Best guess · low
Yes — tag HCO-NS-14, last billed March to the co-op.
- Port took the meter in the 2024 lease.
- It is shared with the ice plant; we need a split letter.
- 0.63q-01 · #03
Can the 2019 truss take 22kg/m² ballast without sistering?
Best guess · low · taken
No — the 2019 calc was snow load only. Ballast needs a new stamp.
- Yes if we stay under 16kg/m² and skip walkways.
- Sister two bays on the north edge and it holds.
- 0.73q-04 · #04
Is the October storm window still 4–11 Oct on bulletin 14-B?
Best guess · low
Yes — bulletin 14-B is still posted at the harbor office.
- Moved up to 28 Sep–3 Oct after the August squall.
- Window cancelled; rain only, no named storm.