Assumption-first factory

Least Sure

North shed solar · Harbor co-op · north shed roof/Beat the October storm

Grok 4.6 lowGrok 4.6 xhigh
0:55
W-0329 · 1 min wake
Stale wake: popped work has no new evidence. Add progress or wake will keep saying so.

Least sure first

Questions, guesses, alternatives. Sorted by lowest confidence. Ties break on id.

  1. 0.56
    q-02 · #01

    Will SMA ship 3× STP 10.0 before 22 Sep?

    Best guess · low · taken

    No — SMA quoted 28 Sep, six days after the pull-in we need.

    • Yes if we take 8.0s from stock and rewire the strings.
    • Buy used 10.0s from Pier 2 this week.
  2. 0.57
    q-03 · #02

    Does the co-op still own the north-shed meter?

    Best guess · low

    Yes — tag HCO-NS-14, last billed March to the co-op.

    • Port took the meter in the 2024 lease.
    • It is shared with the ice plant; we need a split letter.
  3. 0.63
    q-01 · #03

    Can the 2019 truss take 22kg/m² ballast without sistering?

    Best guess · low · taken

    No — the 2019 calc was snow load only. Ballast needs a new stamp.

    • Yes if we stay under 16kg/m² and skip walkways.
    • Sister two bays on the north edge and it holds.
  4. 0.73
    q-04 · #04

    Is the October storm window still 4–11 Oct on bulletin 14-B?

    Best guess · low

    Yes — bulletin 14-B is still posted at the harbor office.

    • Moved up to 28 Sep–3 Oct after the August squall.
    • Window cancelled; rain only, no named storm.